• Alignment: Melrose Turnout to Cannon AFB/Clovis FW Tanks

  • 9 miles of 33-inch Welded Steel Pipe/16-inch Ductile Iron

  • Field Work, Design, & Legal Descriptions– Completed

  • $25M – Estimated Construction Cost

Easement Status

  • Easement Acquisition – In Progress (18 total, 15 secured)

                                                                                                                                                                                                                                                                  CAO January 8, 2018

                                                                                                                                                                                                                                                                 CAO January 8, 2018