Intake structure

 
  • Construction Started in February 2013 and was completed in April of 2016.  

  • Construction cost - $14M.

 

Facility Construction

  • Shaft (51 feet diameter by 93 feet deep)

  • Intake Screen bench (65 feet deep by 115 feet wide)

  • Intake Tunnel (54 inches diameter by 250 feet long)