PROJECTS
Hover over the dots on the map to see more information about each project
Intake and Intake Pump Station
Intake Status: Completed
Intake Cost: $19.2 Million
Intake Pump Station: Awaiting Funding ($48.8 Million estimated)
Intake includes a 51’ x 93’ deep shift, 65’ deep x 110’ wide intake screen bench and 54” tunnel that is 250’ long
Raw Water One A PipelineRaw Water One A Pipeline
Status: Construction to Begin Soon
Cost: $98.3 Million
Will transport water from intake pump station to the north and raw water Pipeline One B, 14.5 miles of 42” welded steel pipe
Raw Water One B & Raw Water Two PipelinesRaw Water One B & Raw Water Two Pipelines
Status: Bidding in fall/winter 2026
Cost: $135.8 Million
Raw Water One B will transport water from the south and Raw Water Pipeline One A to the Caprock Pump Station, 11.6 miles of 42” welded steel pipe. Raw Water Two will transport water from the Caprock Pump Station to Caprock Tank, 4.7 miles of 42” welded steel pipe.
Raw Water One B & Raw Water Two PipelinesRaw Water One B & Raw Water Two Pipelines
Status: Bidding in fall/winter 2026
Cost: $135.8 Million
Raw Water One B will transport water from the south and Raw Water Pipeline One A to the Caprock Pump Station, 11.6 miles of 42” welded steel pipe. Raw Water Two will transport water from the Caprock Pump Station to Caprock Tank, 4.7 miles of 42” welded steel pipe.
Caprock Pump StationCaprock Pump Station
Status: Awaiting funding
Cost: $54.5 Million (estimated)
Will receive water from Raw Water Two pipeline and pump it to the Caprock Tank
Caprock TanksCaprock Tanks
Status: Awaiting funding
Cost: $22.9 Million (estimated)
Will connect Raw Water Two pipeline to Raw Water Three pipeline
Raw Water Three PipelineRaw Water Three Pipeline
Status: Under Construction (About 55% complete)
Cost: $91.9 Million
Will transport water from the Caprock Tank to the Water Treatment plant, 22 miles of 42” welded steel pipe.
Water Treatment PlantWater Treatment Plant
Status: Awaiting Funding
Cost: $341.9 Million (estimated)
Will use ultra filtration membranes and reverse osmosis to treat and deliver as much as 28 million gallons a day (mgd) of drinking water
Finished Water One PipelineFinished Water One Pipeline
Status: Completed
Cost: $75.3 Million
Will connect water treatment plan to the main junction between Finished Water Two and Finished Water Three A Pipelines, 15.5 miles of 39” welded steel pipe
Finished Water Two Pipeline & Canon LateralFinished Water Two Pipeline & Canon Lateral
Status: Completed
Cost: $30.3 Million
Will connect Finished Water One pipeline to the Clovis Finished Water Tanks, 7.5 miles of 33” welded steel pipe and 16” ductile iron pipe
Finished Water Three A PipelineFinished Water Three A Pipeline
Status: Completed
Cost: $22.6 Million
Will connect Finished Water One pipeline to Finished Water Three B pipeline, 13.2 miles of 20” PVC (polyvinyl chloride) and ductile iron pipeline
Finished Water Three B PipelineFinished Water Three B Pipeline
Status: Completed
Cost: $22.1 Million
Will connect Finished Water Three A pipeline to Portales Finished Water Tanks
Portales Finished Water TankPortales Finished Water Tank
Not part of ENMWUA but will include Portales’ allocation of drinking water
Elida Pump Station 1AElida Pump Station 1A
Status: Awaiting funding
Cost: $3.9 Million (with Elida Pump Station 2B)
Will boost water pressure to the Elida Lateral
Elida LateralElida Lateral
Status: Awaiting Funding
Cost: $40.3 Million (estimated)
Will connect Finished Water three pipeline to the Elida Finished Water Tanks, 30 miles of HDPE (high-density polyethylene) pipe
Elida Pump Station 2BElida Pump Station 2B
Status: Awaiting Funding
Cost: $3.9 Million (with Elida Pump Station 1A)
Will boost water pressure to the Elida Lateral
Elida Finished Water TankElida Finished Water Tank
Status: Awaiting Funding
Cost: Will be included as part of the estimated cost to complete the project.
Will store drinking water for use by Elida
Texico LateralTexico Lateral
Status: In construction (55% completed)
Cost: $11 million
Will connect Clovis to the Texico Finished Water Tanks, 4.2 miles of 8” HDPE high-density polyethylene) pipe
Texico Finished Water TankTexico Finished Water Tank
Status: Awaiting Funding
Cost: Will be include as part of the estimated cost to complete the project.
Will store drinking water for use by Texico
The Eastern New Mexico Rural Water System, operated by ENMWUA, includes:
- An Intake Structure at the Ute Reservoir
- Four Raw Water pipelines totaling 52.8 miles
- Four Finished Water pipelines totaling 41.2 miles
- Three Lateral pipelines totaling 43.7 miles
- A Treatment Plant that will produce up to 28 MGD (millions of gallons a day) of drinking water
- Four pump stations
- Two 3-million-gallon storage tanks at the top of Caprock
Click on one of the titles below to learn more about that project.